Mai Beni Hydropower Project - 9.51 MW

Project Developed By
Salient Features
  • Installed capacity: 9.51 MW
  • Project Location: Maijogmai Rural Municipality & Ilam Municipality, Ilam district, Province - 1
  • Type of Scheme: Run-of-River (RoR)
  • Gross Head: 147.5 m
  • Net Rated Head: 134 m
  • Design Discharge: 8.4 m3/s
  • Net Annual Energy: 53.28 GWh
  • Headrace tunnel: 2565 m
  • Headrace pipe: 1789 m
  • Power Evacuation to: Godak Substation ( 4 km from Powerhouse) 
Project Brief

Located in the middle reach of Mai river in Ilam district of eastern part of Nepal, Mai Beni Hydropower Project is a Run-of-River type hydropower project with an installed capacity of 9.51 MW. The Project is the pilot project of Urja Developers Pvt. Ltd., and has embarked on construction since May 2018. The components of the project lie between an elevation of 490m and 645m above mean sea level. All the major components of the project are within 5 km distance from Mechi highway. At present, full-fledged construction works are ongoing.


Progress Updates

•    Construction of access road and other site enabling works completed
•    Detail engineering design completed
•    Financial Closure concluded with Nepal SBI Bank Ltd. as a lead bank and Siddhartha Bank Ltd. as a member bank.
•    Construction activities advancing in full swing 
•    Construction of Headworks structures completed 
•    Installation of pipe, anchor block construction and backfilling works substantially completed at Headrace pipe 1
•    Installation of pipe, anchor block construction and backfilling works substantially completed at Headrace pipe 2 and Penstock
•    Excavation and lining works of Headrace Tunnel 1 completed
•    Excavation works at Headrace Tunnel 2 completed and tunnel lining works in progress
•    Construction of Permanent camp completed
•    Construction of Transmission line in progress
•    Construction of Powerhouse and Tailrace completed
•    Protection works at Powerhouse and Tailrace Canal completed
•    Surge pipe installation works in progress
•    Manufacture of all the electromechanical equipment completed and delivered to site; Installation of electromechanical equipment at Powerhouse in progress
•    Installation of Hydromechanical components at Undersluice, Intake, Settling Basin, Approach Canal, Tailrace and Trash passage in progress

 

Key Milestones
Power Purchase Agreement - Nov 2016

Power Purchase Agreement was signed with Nepal Electricity Authority in November 2016.

Generation License - Apr 2018

Generation License was obtained from the Department of Electricity Development in April 2018.

Construction Start - May 2018

The project embarked on construction in May 2018 after the award of civil works contract to CE construction.

Financial Closure - Dec 2018

Financial closure was concluded in December 2018 with Nepal SBI Bank Ltd. as a lead bank and Siddhartha Bank Ltd. as a member bank.

Required Commercial Operation Date - Nov 2021

The Required Commercial Operation Date (RCOD) as per the power purchase agreement is Nov 2021.